Johnstone Construction Operations Manager Susy Pyrde said the site is a hive of activity with great progress happening.
On the western half of the slab, reinforcing is being installed along with sighting brackets and the second layer of slab boxing. Just around the corner, blocks have been installed on the basement ramp.
SignOnSite recorded 12 companies on site last week, with a combined total of 386 man hours.